Monitoring Well Destruction, Replacement, and New Installations at Various Locations Soquel, Capitola, and Aptos, CA

HydroMetrics Water Resources Inc. (HydroMetrics) | June 14th, 2012


A total of six new monitoring wells and seven replacement monitoring wells were drilled and constructed, and 13 monitoring well destroyed between February 7 and April 26, 2012 for the Soquel Creek Water District (District). This work took place at six different locations in the Soquel-Aptos area. The work was accomplished in order to meet the basin management objectives of the Soquel-Aptos Groundwater Management Plan (Soquel Creek Water District and Central Water District, 2007) and recommendations made in the Water Year 2010 Annual Report and Review (HydroMetrics WRI, 2011). A summary of the work performed and monitoring well construction details at each of the six locations are provided below. 